Ampteks Portfolio

Image

Electrical Testing - Thermography - Onsite Circuit Breaker Repair - Onsite Support

Ampteks provides electrical maintenance testing and switchgear maintenance not only in the Bay Area, but also the Central Valley. Whether if it’s one breaker or a full facility shutdown you can be confident that Ampteks has the required skill set and training to complete the job on time and resolve the majority of issues that arise during your shutdown.

Image

365 Main

Emergency repair of two MagnumDS breakers. Both breakers had issues comminicating with the external PLC logic. Issues where resolved by replacing the OTS on one and the Aux switch on the second breaker.

Image

Applied Materials

We perform the annual shutdowns for multiple AMAT facilities that involve thousands of breakers, transformers, relays, ect.

Image

Avaya

A water main break flooded the electric room and switchgear. Ampteks was tasked with switchgear and circuit breaker remediation, the job was completed in 24hrs.

Image

Bay Area News Group

Ampteks provided two DS840's to integrate into a transfer switch scheme, we also refurbished and modified two existing DS-840's as spares.

Image

Bloom Energy

Primary injection, Low Voltage Switch, and Ground Fault Testing

Image

Burney Forest Power

Primary injection testing of AK frames, medium voltage breaker and contactor testing.

Image

Covanta Energy

Secondary injection testing of Siemens RL frames. Also transformer, reactor, and transducer testing.

Image

Datapipe

We installed and tested over 100 AC-Pro-MP trip unit retrofit kits in Masterpact MP frames.

Image

Intel SC2

Switchgear maintenance and testing.

Image

Intel SC11

22 GE AKRU trip unit retrofit with Entelliguard, maintenance and testing.

Image

Intel SC 12

Powerbreak II mechanism repair. Replaced 24 rebound dampeners which cause the breaker not to charge. We have performed 500+ repairs on Powerbreak II for this problem.

Image

Lam Research

Secondary injection testing, medium voltage breaker and relay testing, GFI testing.

Image

Lucile Packard Childrens Hospital

We have performed IR, maintenace testing, and repairs for LPCH more than a decade.

Image

Microsoft

Red eye maintenance testing.

Image

Nest

Maintenance testing for multiple buildings at Nest labs.

Image

Nest

Adding charging motors, close coils and shunt trips.

Image

Superior Court of California

We performed switchgear maintenance and testing on two San Mateo County Courthouse buildings, first maintenace in a very long time...

Image

Tesla Motors

Cutler Hammer VCP-WR DHP retrofill maintenance testing

Need a Report? No Problem

Submit your request Image

Image

Get your report emailed Image

Image